Sarikoy Project Execution

After we raised enough funds to start the repairs for Sarikoy, our dedicated volunteer Mehmet Okur went to Midyat, Mardin to visit local authorities, get permissions, finalize the action plan, find a contractor, and negotiate prices for this project.

Click here to see some Turkish news coverage of our efforts in a local newspaper.

Once we received his comprehensive report on July 29th, we approved the project start for August 1st. The main repairs went smoothly and were completed on August 10th.

Project Cost

Enlarging the classroom: $148
Roofing: $1,425
Painting: $1,135
Floors: $1,172
Water system & restrooms: $204
Electricity system: $37
Other repairs: $59
Operational expenses: $300

Total Repair Costs: $4,480

We will channel the rest of the funds to provide basic school supplies to the students of Sarikoy Elementary School.

Please click here to learn more about the construction and see photos during the Sarikoy renovations.

 

Project Introduction

Sarikoy Project Brochure

Fundraising for Sarikoy

Donor Roll for Sarikoy

Updates as of August 12, 2005

List of Items Sent

Project Completion

Sarikoy Photos

 

Back to Sarikoy Main Page


VISION

To contribute to peace and democracy by encouraging the growth of Turkish civil society.

 

MISSION

To strengthen community participation by supporting education, promoting volunteerism and philanthropy, and fostering cultural exchange.

 

Donate Now!

To make online donations, please click on the icon below.

 

 

For check donations or other ways to support us, please click here.

 

 

 

 

Home About Us Programs Volunteer Donate Contact Us

Friends of Anatolia is a tax-exempt nonprofit organization

under section 501 (c) (3) of the Internal Revenue Code.

Federal ID # is 20-1253666 and California State ID # is 2626411

Please read our privacy policy.

Site last updated: December 23, 2006, ©2005-2006 Friends of Anatolia

1